1. According to the average temperature specification, the data map of the installation sequence of the steel components is compiled, and the installation is carried out in strict accordance with the sequence during construction.
2. When assembling the space frame components, expand and assemble from the inside to the outside according to the order specified by the process, and do a test to determine the shrinkage value of the weld that needs to be reserved during the assembly at low temperature.
3. When the steel components are made at normal temperature and installed at low temperature, the shrinkage of the components should be fully considered according to the difference in ambient temperature, and technical measures to adjust the deviation should be taken during construction.
4. The columns and main beams installed at negative temperature should be corrected immediately. After the correct position correction, they should be permanently fixed immediately. The components installed on the same day should form a stable space system.
5. When the high-strength bolted joint is installed, the friction surface of the component shall not have snow and ice, and shall not be in contact with dirt, oil and other stolen goods.
6. When using steel cables to hoist steel components, anti-slip spacers should be added, and the gusset plates that are lifted at the same time as the components, and the fixtures and other items that the installer needs to use are securely tied with ropes.
7. When the steel structure space frame is installed on site, it is necessary to build a protective shed in case of rain and snow or when the wind speed is above 6m/s.